Guide

BNG exemptions: the full gov.uk list for 2026

Updated

The exemptions changed in 2026, and the change is significant enough that schemes previously caught by BNG may no longer be. This is the list as gov.uk states it.

Get BNG quotes

The exemptions

  • Applications made before 12 February 2024. gov.uk: any planning applications for developments made before that date are exempt.
  • Small (minor) developments applied for before 2 April 2024. gov.uk: any planning applications for small developments made before that date are exempt.
  • Developments of 0.2 hectares or below. gov.uk: from 6 August 2026, BNG does not apply to planning applications for developments where the site area within the red line boundary is 0.2 hectares or below.
  • Householder applications, including home extensions, conservatories and loft conversions, as defined in article 2(1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015.
  • The de minimis rule, where the development impacts less than 25 square metres, that is 5 metres by 5 metres, of on-site habitat, or less than 5 metres of on-site linear habitats such as hedgerows.
  • Temporary developments. gov.uk: from 6 August 2026, BNG does not apply to short-term developments if the whole development is temporary and planning permission is granted for 5 years or less.
  • Self-build and custom build, where planning permission was applied for before 6 August 2026, or a variation is applied for on or after that date and the original permission was exempt. gov.uk: the exemption no longer applies to new applications made on or after 6 August 2026.
  • Off-site BNG gain sites, that is developments creating or enhancing habitats solely or mainly to fulfil a BNG planning condition.
  • High-speed rail, for development that is part of, or ancillary to, the high-speed railway transport network.
  • Crown development and permitted development rights, as exempted under the Environment Act 2021.

gov.uk: if a development impacts priority habitat on site, the 0.2 hectare, de minimis and temporary development exemptions do not apply and BNG must be met. A development impacts a habitat if it decreases its biodiversity value (gov.uk: BNG exempt developments, read 2 November 2026).

Exempt does not mean nothing to do

Two things still bite when a development is exempt from BNG:

  • Most authorities expect an exemption statement or the relevant declaration with the application. Getting it wrong is a validation problem rather than a planning one.
  • BNG is not the whole of ecology. Protected species, priority habitats, tree protection and local plan biodiversity policies all apply whether or not the statutory 10 percent does.

A site with an active badger sett or a bat roost has exactly the same obligations whether or not it clears the 0.2 hectare threshold.

Before you rely on an exemption

  1. Measure the red line area properly, not the developable area. The 0.2 hectare test is stated by gov.uk by reference to the site area within the red line boundary.
  2. Check the date your application was made, since several of the exemptions are date-based.
  3. Read the gov.uk exempt developments page in full rather than a summary, including this one, and check the local planning authority's own validation requirements.
  4. Get it confirmed in writing where an exemption is load-bearing for your programme. A wrongly claimed exemption discovered at validation costs a survey season.

Exemptions are quoted from gov.uk guidance on BNG exempt developments, linked in the sources below. Guidance in this area has changed repeatedly, so check the current page before relying on it.

Get BNG quotes from ecology consultants

Two minutes of questions; ecology consultants covering your site quote you directly. Free, no obligation.

Your site

What are you developing?

Sites up to 0.2ha are BNG-exempt from 6 August 2026.

  • Free, no obligation
  • Your details go to at most three consultants
  • Takes about two minutes

Get a fee against your actual site.

Two minutes of questions; ecology consultants covering your site quote you directly. Free, no obligation.

Questions, answered directly

Which developments are exempt from biodiversity net gain?

GOV.UK lists exemptions including applications made before 12 February 2024 and small developments applied for before 2 April 2024. From 6 August 2026 they include developments of 0.2 hectares or below, and temporary developments permitted for 5 years or less. Self-build with permission obtained before 6 August 2026 is exempt. So are householder applications and impacts under the de minimis 25 square metres of habitat or 5 metres of linear habitat. Off-site gain sites, high-speed rail development and certain Crown and permitted development are too.

What is the BNG small site exemption?

GOV.UK states that from 6 August 2026 BNG does not apply where the site area within the red line boundary is 0.2 hectares or below. That holds unless the development impacts priority habitat on site. Measure the red line area, not the developable area, and confirm with the local planning authority before relying on it.

What is the BNG de minimis exemption?

gov.uk: BNG does not apply to a development that impacts less than 25 square metres (5m by 5m) of on-site habitat within the red line boundary. Nor does it apply below 5 metres of on-site linear habitat such as hedgerows. It does apply where priority habitat on site is impacted.

Is self-build exempt from BNG?

Only for planning applications made before 6 August 2026. Or for a variation applied for on or after that date where the original permission was exempt. GOV.UK states the self-build and custom build exemption no longer applies to new applications from 6 August 2026. A small self-build may still fall under the 0.2 hectare exemption.

Sources

This site's own datasets, every figure quoted from its source and dated:

  • The median published figure in the BNG Assessment Price Index is 492 GBP across 6 sources' own pages (range 295 to 589 GBP), read 10 November 2026.
  • The BNG Statutory Requirements carries 6 published figures read from 1 source's own page, from 44,000 to 650,000 GBP, read 7 November 2026.
  • The BNG Unit Market Index carries 23 published figures read from 4 sources' own pages; the 21 published figures given by habitat run from 15,000 to 165,462 GBP, read 10 November 2026.
  1. gov.uk, understanding biodiversity net gain
  2. gov.uk, biodiversity net gain exempt developments
  3. gov.uk, statutory biodiversity credit prices
  4. gov.uk, buy statutory biodiversity credits
  5. gov.uk, statutory biodiversity metric tools and guides
  6. legislation.gov.uk, Environment Act 2021
  7. legislation.gov.uk, Environment Act 2021, Part 6 (nature and biodiversity)
  8. gov.uk, biodiversity net gain guidance collection