Guide
Biodiversity net gain guidance: the requirements gov.uk sets
Updated
BNG is a statutory scheme under the Environment Act 2021. This page states the requirements as gov.uk states them, with nothing added.
Biodiversity net gain planning requirements
- The gain
- gov.uk: developers must deliver a BNG of 10 percent. The purpose is that habitats are in a measurably better state than they were before the development.
- The biodiversity net gain metric
- gov.uk: there is a statutory biodiversity metric which you must use to measure biodiversity units, using the statutory biodiversity metric tool.
- The biodiversity net gain plan
- gov.uk: you will need to create a biodiversity gain plan showing how you will achieve BNG, and the local planning authority must approve or refuse it within 8 weeks.
- The duration
- gov.uk: you must maintain the habitats you create or enhance for a minimum of 30 years, with responsibilities set out in a legal agreement.
- Where it applies
- The guidance applies to England.
BNG legislation
GOV.UK states that in England BNG is mandatory under Schedule 7A of the Town and Country Planning Act 1990. It was inserted by Schedule 14 of the Environment Act 2021 (gov.uk: understanding biodiversity net gain, read 2 November 2026).
So the gain is a condition of the planning permission itself. The biodiversity gain plan has to be approved before development can begin, and the exemptions are set by the same framework rather than by local policy.
The delivery hierarchy
- Create habitat on site. The first option, and normally the cheapest unit available to a scheme.
- Off-site units. Deliver gains on other land you control, or buy units from a habitat bank or landowner. gov.uk notes that from 6 August 2026 small (minor) developments that are not already exempt can consider options 1 and 2 at the same time.
- Statutory biodiversity credits bought from the government, described by gov.uk as a last resort. Prices are published, and 2 credits must be bought for every 1 biodiversity unit compensated for.
When mandatory biodiversity net gain started
| Development type | Date stated on gov.uk |
|---|---|
| General mandatory requirement | 12 February 2024 |
| Small (minor) developments | Applications made before 2 April 2024 are exempt |
| Nationally Significant Infrastructure Projects | 2 November 2026 |
| Site area threshold change to 0.2 hectares | From 6 August 2026 |
Small sites
gov.uk states that for small developments you do not need an ecologist. You can use the simpler small sites biodiversity metric tool yourself, or someone familiar with the site can do a survey and make a calculation.
That is a genuine saving, with a trade-off. A metric calculation that a local planning authority queries costs more in delay than a consultant's fee saved. Habitat condition assessment is the part non-specialists most often get wrong.
Quoted requirements are taken from gov.uk guidance on understanding biodiversity net gain, linked in the sources below. The underlying statute is the Environment Act 2021. Check the gov.uk page before relying on any summary, including this one, because BNG guidance has changed more than once since 2024.